Project data of backfilling plant "Norilsk" in Russia,planned,constructed and commissioned by ENGINEERING DOBERSEK GmbH, linked to "Project Report" and "Picture Gallery using the example of a Backfilling Plant in Kazakhstan"

 
 
 

Backfilling and Pumping Plants for the Transport of Solids in Russia

   
Plant Description: Two CONTICLASS®SYSTEM backfilling plants with separation installations: engineering, construction, mounting and commissioning of turnkey plants for backfilling and supply of a high-pressure pumping plant for the transport of tailings / solids
Site: Norilsk, Russia
Year of Construction: May 2008 – Summer 2009
Technical Data: 250.000 m³ concrete/year (plant 1), 1.000.000 m³ concrete/year (plant 2)
Customer: Mining Combine “JSC MMC Norilsk Nickel” – Norilsk Mining & Nickel Plant
Highlights / Special Features: Total coordination

Project Report           Picture Gallery using the example of a Backfilling Plant in Kazakhstan  

       

 

 

 